DIXON was formed in 1981 to offer full design and field inspection
services for rehabilitation of water storage tanks. Over the ensuing
years, many additional services have been added to keep DIXON on
the cutting edge to serve the needs of the industry.
| Phase One |
Preliminary Maintenance Inspection comes first. This inspection
provides a definitive analysis of the condition of the structure
and the creation of a cost-effective budget picture. |
| Phase Two |
Preparation of technical specifications for the solicitation
of competitive bids. Complete and accurate specifications attract
competent contractors at competitive prices. Good specifications
assist the inspector, protect the owner, and guide the contractor
throughout the entire project. |
| Phase Three |
Continued inspection services as the project progresses. Flexible
scheduling is based on the demands which vary from project to
project. |
| Phase Four |
The one-year warranty inspection. This inspection will detect
defects in materials or workmanship for which the contractor
may be responsible. |
| Phase Five |
Additional maintenance inspections performed every three to
five years to monitor tank conditions. |
One thing that has not changed is the dedicated and professional
approach to each new challenge. Thorough and thoughtful planning
is the key to DIXON's success.
The requirements of each project demand carefully considered flexibility.
The entire DIXON team employs their combined skills and talents
to assure a successful project from start to finish - and beyond.
|